Review-Preview 03/10/26
Last Week: What Moved Forward
Development
- Development Kickoff
- Development Kickoff - Knowledge Transfer was written for BIX and Everett & Co.
- The team was staffed and calls were scheduled.
- MSA, SOW, and Addendum final agreements were executed and W9 received.
- SOC-II & Delve
- Initial onboarding call with Delve to go over the use case for both PreFi & Purlend. Still some details to work out around how tools and access are set up in the beginning, which affects which SOC-II audit runs under which name.
- Sent the access link to the platform but holding off for 30-60 days until development gets going and there is staging level code ($15,000 cost on platform access).
Design
- Design Kickoff
- Design Kickoff - Knowledge Transfer was written for BIX and Everett & Co.
- PSA with Everett & Co was executed and W9 received.
- Independent contractor agreement with Charlie was executed and W9 received.
This Week: What We're Focusing On
Development
- Kickoff on 3/10 and 3/11
- The team is getting up to speed on development and design documents and asking initial questions
Design
- Everett & Co. payment scheduled Monday for the initial invoice.
- Initial call with Everett and his partner scheduled for Wednesday
- Vinny (UI/UX resource from BIX) will be in attendance to ask questions around what can be delivered this week that won't result in duplication
- Staffing of Everett & Co. for the project should be finalized by Friday with a combined official kickoff with BIX and Charlie Friday or Monday, scheduling TBD until team is staffed
Shared Project Plan & Timeline
- Initial plan on team alignment has been pulled together for BIX & Everett & Co. (Bix & Everett Discovery Alignment)
- Finalized plan and roadmap will be produced after discovery kickoff
Internal Tooling & Infrastructure Setup
- Tools provisioned for BIX, will be provisioned for Everett once team is staffed:
- Roam: meeting, chat, and virtual office
- Atlassian Jira: product management
- Atlassian Confluence: product documentation
- GitHub: code repo
- Figma: design
- Additional tools will be implemented based on BIX's recommended stack
- Tools & Subscriptions: tracking tools and access
Open Items / Blockers
- Finalization of redlines (Licensing) sent between Ken & David
- Owner: Ken
- Stakeholders: David
- Due: This week
- Cashflow & COGS planning for the project aligned with financials
- Owner: David / Sydney
- Stakeholders: Ken
- Due: Next week
- Note: In progress, will need updates this week and next after initial kickoff and tooling is finalized. Will continue to evolve as the build does.
- Architecture and compliance assumptions confirmed with partners
- Owner: David
- Stakeholders: Technical teams
- Due: Technical Discovery
Decisions Needed
- Decision: Review the Design Kickoff Knowledge Transfer. Agreement or adjustment.
- Owner: Ken & Taylor
- Stakeholders: Sydney, David
- Due: Wednesday 3/11
- Confirmation: Branding for PreFi would not be considered within the project build budget already agreed to.
- Owner: David
- Stakeholders: Ken
- Due: During Discovery
- Note: Quote from Charlie (design leader) for additional cost, potentially after Phase 1 of Alpha or in concert with discovery.
- Decision: Business licensing + IP structure
- Owner: Ken
- Stakeholders: Sydney, David
- Due: Week of March 1st
- Note: Call with Ken and David weekend of 3/7 with things mostly finalized. A few final notes to sure up.
- Decision: Availability of the data for the propensity to move for Purlend's B2B use case that PreFi could benefit from for the trainings
- Owner: David
- Stakeholders: Ken
- Due: Technical Discovery
Risks / Watchouts
- Licensing & IP alignment risk: Any misalignment or delay in IP structure decisions may impact contracting timelines.
- Team coordination risk: Hybrid model (agency + internal + BIX UI) requires very clear ownership boundaries to avoid overlap or inefficiency. Working on this this week and next. Much more will be clear once Everett & Co. is staffed.